Jump to navigationJump to searchCreate Option Groups and Schedule Builds
Option Groups are simply a way of organizing a name with chosen settings on each of the Student, Transcript and Staff tabs.
- Click the "+" under the options Groups table.
- Enter a name and a description.
- Click the "Save" button in the popup 'Save Option Group' window to have it appear in a row.
- Click on the "-" for deleting after having chosen the option that needs to be deleted.
Schedule Builds
- Create/Choose a schedule using the Start/End Dates and the days of the week for files to be built and sent automatically.
- Click the "Save" button in the popup 'Save Schedule' window to have it appear in a row.
SFTP and URL Settings
- SFTP User - This is the user name to access the SFTP server and should be already defaulted as setup by the IT department.
- SFTP Pass - This is the password to access the SFTP server that comes from PowerSchool. The user should only have to enter and Save (button at the bottom of the page) the EDLink SFTP password to access the SFTP server. Note that this is NOT the same as the EDLink Dashboard password.
- EDLink URL - This is the URL of the EDLink STTP server and should be already defaulted as setup by the IT department.
JDrive Folder
- Storing the file in JDrive is not required and is only for the user's convenience of storing the file for reading, etc.
- Click the field next to "JDrive Folder" and create a folder called "EDLink".
- Single left click on the new "EDLink" folder and click the "Choose" button.
- Click the "Save" button at the bottom of the page.
Build
- Go to the Student, Transcript and Staff tabs first to add settings to the Option Group before building a file set.
- Once the user has created an Option Group and added settings to it, build the files.
- Click Build to build files.
- Choose an Option Group.
- Click "Go!" Build and then Go! is what will build the file to send the file to EDLink.
- Once complete, click the "Send button" and the user is done.
- It can take anywhere from 5-50 minutes to complete.
- At 7pm nightly, EDLink will start processing the most recent file built whether it was a scheduled build or a manual build. Scheduled builds are automatically built and then sent at 4pm.
- File results should be posted to the EDLink dashboards the next day by 7AM.
Status - Click Status to see the Task Status window displaying the current file build status(es).
- Current tab shows the jobs in progress or to be done with the following statues. Clicking on the Current tab will automatically refresh, giving you information about the processing. After the file has finished processing, the Current tab screen will be blank.
- Pending - This status indicates that the file is waiting to process.
- Start - This status indicates that the file is gathering the records to process.
- Running - This status indicates that the file is processing. There will be a progress bar and a Report: current date/clock time.
- Completed tab shows completed jobs and will display columns of information about the files that have been built. The user can click anywhere on the rows of the completed jobs to see and also print errors or warnings. These are Send and Build errors. Check the Print By School to have different schools printed on separate pages.
- siEDLinklLogic xx.xx.xx - This is the program name that is being used with the version (xx.xx.xx) number of the program.
- Progress Bar - This shows the number of completed records processed.
- Status - The status will always be Finish.
- Report: date/time - This information will be used to identify which file(s) you must use when submitting for state reporting.
- Start and Finish - This is the date and time of starting and finishing the task.
Send - Click Send once files have been manually built.
Example to Build a File Set to Go to EDLink for State Reporting
- Go to the 2021 school year and the EOY Option Group and select options for Student (SIS), Transcripts (STS) and Staff (PEP).
- Click the save button on each tab.
- Once done, go to the "Schedule" tab and click "Build", select the EOY Option Group and then click "Go!".
- This will build the file set.
- Once complete, click the "Send button" and you will be done.